OLD STONE SCHOOL RENOVATION, ± 10,400 SF

JULY 8, 2002

 

PRELIMINARY COST ESTIMATE

 

Roof Replacement – 5200 SQ @ $20 .......................................... * $104,000

Exterior Fascia and Trim – 600 LF @ $100 ......................................... 60,000

Asbestos Removal (Allowance) ........................................................... 10,000

HVAC – Heating – 10,400 SF @ $8 .................................................. 83,200

Electrical – 10,400 SF @ $12 ........................................................... 124,800

Plumbing – 10,400 SF @ $4 ............................................................... 41,600

HVAC – Cooling – 10,400 SF @ $10 .............................................. 104,000

Exterior Masonry ± 9,000 SF @ $2 .................................................... 18,000

Exterior Windows (Allowance) ............................................................ 75,000

Sprinkler System – 10,400 SF @ $4 ................................................... 41,600

Interior Walls Finish – 10,400 SF @ $5 ............................................... 52,000

Interior Doors and Hardware (Allowance) ........................................... 60,000

Interior Trim – 10,400 SF @ $10 ...................................................... 104,000

Interior Floors – 10,400 SF @ $7 ....................................................... 72,800

Site Work/Landscape/Lighting (Allowance) .......................................... 50,000

Stair Addition, Link – 400 SF @ $100 ................................................ 40,000

 

                                                               Subtotal.......................... $1,042,000

 

                                                               Contingency 10%................ 105,000

                                                              

                                                                                                      $1,147,000

 

                                                               A/E Fees 12%                      137,000

 

                                                               Grand Total                     $1,284,000

 

Additive Options

 

Porch ................................................................................................ $40,000

Elevator ........................................................................................... $120,000

Foundation Work ............................................................................ $125,000

* Roof may be adequate (need to confirm).......................................................